Friday, 25 July 2014

North pavilion taking shape!

After months of below ground and foundation work, hidden by the compound walls, the new bedroom block in the north pavilion is progressing at a rapid rate with brickwork now up to ceiling height on the first floor. The week commencing 28.7.14 will see the concrete slabs, which form the ceiling for first floor rooms and also the slab for the second floor rooms, be craned into position. The brickwork will then continue in earnest until the process is repeated for the next level three weeks later.

The degree of progress made in recent weeks now clearly defines the floor plan of the ground and first floor level bedrooms and corridor. Of the twelve new guest bedrooms in the north pavilion, two have been designed taking careful consideration for guests with restricted mobility. The floor plan of this north pavilion extension varies slightly from the existing four block which is located closer to the study centre, as the staircase and lift will be housed in the link to the main building, meaning the new bedrooms will be slightly larger.

For the readers wanting a more technical update, the concrete block work which forms the inner and structural walls of the north pavilion are surrounded with Kingspan foil back rigid insulation, an important layer to help reduce heat loss and solar gain. The outside layer of honey coloured bricks to match the existing building are erected leaving a gap for circulation allowing the building to “breath”. The handmade Stamford Sand Brown bricks, made in York, are the closest match we could achieve to the original Stamford brick which is no longer in production. The Portland Stone horizontal bands have been cut to match the original stone work and are not a cheaper reconstituted product.

Thursday, 26 June 2014

New patio for the Study Centre



Although the majority of the building works are concentrated around the main building, we are also undertaking hard and soft landscaping works to improve the area around the study centre. The first of six phases is now complete – a newly created patio to the west side of the study centre building, just to the left of the main entrance as you approach. This patio has outdoor seating and is designed to be used for dining, networking or even working space (provided the weather permits)! 



Tuesday, 10 June 2014

Developments on the north pavilion



The new administration wing for the back of house staff, located between the existing and new bedroom blocks, is really beginning to take shape. Its roof incorporates three large windows (seen here in the photo) to ensure the open plan office is flooded with natural light. This centralised office will improve internal efficiency at the heart of the business.

Adjacent to the office, in the basement of the new bedroom block (located in the foreground of the photo) will be housekeeping storage and a second passenger lift. The concrete that forms the roof of this area and also the base of the new ground floor bedrooms has now been poured. Brickwork to build the structure up will commence next week.


Friday, 9 May 2014

The only way is up!



After weeks of digging, further steel work and several concrete deliveries, the foundation slab in the north pavilion has now been laid. This marks a very significant point within our project, as we will start to build upwards from now on. The sales and events teams took a trip to the site with Gillian Secrett, CEO, and Stuart Websdale, General Manager, to get a better idea of what their new office space will look like.


Wednesday, 23 April 2014

No more digging!


All the excavation work on both the north and west compounds is now complete. The current focus is on preparing the steel reinforcement for the foundations in preparation for the first concrete delivery on 28th April. We are excited to reach this stage in the development because from this point on the programme is less susceptible to the elements!



Monday, 31 March 2014

Appointment of Mechanical and Electrical contractors

A building extension of this scale naturally requires considerable research into suitable materials and sourcing appropriate suppliers. The Møller Centre is committed to sourcing quality solutions with a view to supporting the local economy and maintaining high levels of environmental performance.

We are delighted to confirm that Bower Fuller, who are based in Suffolk, and have a well established Cambridge team, have been appointed the Mechanical and Electrical contract. Bower Fuller are the second biggest appointment behind the main contractors Morgan Sindall, who are based in Sawston, which is only 12 miles from the Centre, further demonstrating our commitment to the local economy and the environment.

Thursday, 20 March 2014

Latest news - North Compound

The picture below shows the latest developments within the north compound area of the build project, adjacent to the colonnade. The location of the original steps (that used to lead from the Main Building to the Study Centre) can be seen at the top of the picture. The current excavation depth is now clearly visible.