Monday 24 February 2014

North pavilion takes shape



The North pavilion (which is located between the main entrance colonnade and the existing bedroom block adjacent to the car park) is taking shape, with the steel structural sheet piling now complete. 

This structural technique, helps form the load bearing walls and assists in the safe excavation of soil in preparation for the foundation slab to be poured. The sheet piling defines the outline of the north extension. 

For those coming to the Centre, the sheet piling is clearly visible from the second floor. This north extension will consist of 12 new en-suite air conditioned bedrooms, including two accessible rooms to accommodate guests with disabilities, and six that are king rooms capable of converting into twins. Extensive back of house areas are also accommodated in the north pavilion, for storage and the staff office space.

Stuart.

Tuesday 11 February 2014

The new staircase at the end of the Main Building and opposite the Study Centre entrance is currently closed. We will update you once it is opened.

Friday 7 February 2014

A new staircase has been erected between the Main Building and the Study Centre. This will make things convenient for clients and staff wanting to travel between the two buildings during the build project. The staircase will be available to use from tomorrow (Saturday 8th February).

Tuesday 4 February 2014

A focus on furniture this week as we look to source additional Danish Wegner furniture for the new build areas to compliment our existing Wegner pieces, and continue our commitment to the Wegner range.